Regulation · Applied to data centres

Two-part tariff for data centres: captive versus third-party under Vietnam's July 2026 pilot

The short answer — captive and third-party data centres face different two-part tariff outcomes because Circular 60/2025 put them on different underlying tariffs. The captive advantage narrows, but does not reverse.

Page current as of 24 April 2026. Anchor regulation: Decree 146/2025/NĐ-CP, pilot real billing from 1 July 2026. See the full two-part tariff explainer.

Is my data centre in the July 2026 two-part tariff pilot?

Captive data centres — yes. Third-party data centres — genuinely uncertain. The pilot was scoped using a pre-Circular 60 customer universe and has not been re-scoped publicly to address the tariff-class reclassification that happened between the pilot design and its effective date.

Decree 146/2025/NĐ-CP defines pilot eligibility through three conditions, all of which are structural rather than tariff-class based:

  1. Consumption threshold — average monthly consumption of at least 200,000 kWh over the prior 12 months
  2. Voltage threshold — grid connection at 22 kV or higher
  3. Customer type — originally framed around "manufacturing customers" in the Decree text and EVN's pilot documentation, with hospitality and commercial customers excluded

A captive data centre — one operating as a shared IT facility inside a larger enterprise or industrial group, with no external tenants paying for rack space — sits on the manufacturing tariff under Circular 60/2025's December 2025 reclassification. It meets all three conditions and is clearly in the pilot.

A third-party data centre — one selling colocation, managed hosting, or hyperscale-lease capacity to external customers — was moved onto the commercial (kinh doanh) tariff by Circular 60/2025. The commercial tariff is formally excluded from the pilot. But the data-centre sector's ≥200,000 kWh/month consumption and ≥22 kV voltage characteristics mean these operators sit uncomfortably between "pilot cohort by size" and "excluded by classification." MOIT has not publicly clarified which test controls.

In practice: three different readings are circulating in the Vietnamese C&I market as of April 2026. The first: third-party data centres are out, because commercial-tariff customers are excluded. The second: they are in, because the pilot was designed around the pre-Circular 60 universe where commercial-scale data centres were on the manufacturing tariff, and the scope text has not been amended. The third: scope will be decided case-by-case at the EVN regional corporation level when pilot onboarding begins. Any data-centre operator making commercial decisions against a July 2026 trigger needs a written position from their EVN regional corporation before 1 July 2026, not an assumption.

Why the two-part tariff reshapes data-centre economics

Three channels matter. Each is structurally different from how the two-part tariff affects a factory, because data-centre load profiles differ from manufacturing load profiles in ways the pilot does not reward.

4.1 · Energy-band compression hits arbitrage revenue

Under Decision 1279/QĐ-BCT, the current peak-to-off-peak spread is VND 2,208/kWh for 22 kV manufacturing and VND 3,416/kWh for 22 kV business. Under the two-part tariff pilot, EVN's published energy rate ranges (off-peak VND 843–904, standard VND 1,253–1,332, peak VND 2,162–2,251) compress this to roughly VND 1,300–1,400/kWh — a reduction of about 35–40% in the peak-to-off-peak spread.

Battery storage sized for energy arbitrage alone — charging at off-peak, discharging at peak — earns roughly one-third less revenue per cycle under the pilot than under Decision 1279. This hits both captive and third-party data centres equally once either enters the pilot. The compensating mechanism is the capacity-charge saving from peak-shaving, which data centres struggle to capture (see §4.2 below).

In practice: Arcus's factory models rely on arbitrage as a secondary revenue stream layered onto capacity-charge savings. For data centres, arbitrage is usually the primary revenue stream, so the compression matters more. A BESS business case at a data centre sized against the current VND 3,416 spread will not survive re-sizing against a VND 1,350 spread without material increase in dispatch depth or cycles per year.

4.2 · Data-centre load profiles do not reward peak-shaving

The two-part tariff rewards customers who can flatten their demand profile. The capacity charge is billed on registered maximum demand (Pmax), so every kilowatt shaved off Pmax saves VND 235,414 per month at 22 kV, in perpetuity. At a factory with a peaky shift pattern, this is the main economic driver of a BESS investment — 15–20% of Pmax is a realistic peak-shaving target.

Data-centre load works differently. IT load is near-flat by design — that is the defining product characteristic of a data centre. The variability that exists comes from two sources that BESS cannot economically reshape:

  • Cooling overhead — HVAC and chiller load scales with ambient temperature and adds a predictable afternoon peak of roughly 15–25% above the IT baseload. A 4-hour BESS can flatten part of this but is sized for it, not sized to eliminate it
  • Redundancy overbuild — N+1 cooling and N+1 power infrastructure force the operator to declare a Pmax that reflects fully-redundant capacity, not the lower figure that actual load hits. The Pmax declaration is set by what the site could draw, not what it typically does draw

Both mean the capacity-charge saving from BESS at a data centre is structurally smaller than at a factory of comparable consumption. A 5 MW BESS at a 20 MW factory might shave 3 MW off Pmax; the same BESS at a 20 MW data centre might shave 0.5–1 MW if the operator is conservative about redundancy reservations, which they almost always are.

In practice: when pricing BESS for data-centre customers, lead the economics with arbitrage and backup-value displacement. Capacity-charge saving is a real third revenue stream but typically smaller than the factory-case reader would expect. The anchor page note that "BESS economics rely more on outage-backup and site-resilience value than on peak-shaving" for flat-load data centres is directionally correct; this page quantifies why.

4.3 · Captive advantage narrows but does not reverse

Circular 60/2025 moved third-party data centres onto the commercial tariff effective 2 December 2025, raising their blended electricity cost by 45–55%. Captive data centres stayed on the manufacturing tariff and were unaffected. That gap is a direct cost advantage for a single-tenant enterprise data centre versus a colocation competitor, and it has visibly reshaped the Vietnamese colocation pricing conversation since December 2025.

The two-part tariff narrows this gap through two mechanisms. First, if the ambiguity on third-party pilot scope resolves toward "in," both cohorts face the same arbitrage-spread compression, but third-party DCs benefit proportionally more because their starting bill is higher — every 1% reduction in variable-rate exposure saves them more VND than the equivalent reduction saves a captive. Second, the capacity charge falls proportionally more heavily on captive data centres because captive load is flatter and harder to reduce through peak-shaving, removing an offset the third-party cohort can at least partially capture.

A reasonable directional estimate, using Arcus's working assumptions on typical Pmax declarations and utilisation: the 45–55% Circular 60 gap narrows by 5–10 percentage points once the two-part tariff activates and both cohorts are in the pilot. Captive still pays materially less overall — the advantage does not reverse — but the competitive case for the captive architecture becomes less absolute than Circular 60 on its own made it look.

In practice: data-centre operators making 2026–2028 build-versus-lease decisions should not overweight the Circular 60 captive advantage as it stood in December 2025. That advantage narrows when the two-part tariff activates, and will narrow further if the 2028–2030 rollout extends to all commercial customers under Politburo Resolution 70. A decision that only pays back under the full Circular 60 gap is a fragile decision; one that pays back under a narrower gap is robust.

Two-part tariff terms most relevant to data-centre operators

Keeping this brief. The anchor page covers the full framework — this section calls out what a data-centre operations or procurement team specifically needs to know when evaluating pilot exposure, Pmax strategy, or DPPA interactions.

For the full regulatory text explanation — Article 50 of the Electricity Law, Decree 146 implementing mechanics, capacity-rate grid by voltage band, Pmax true-up process, pilot-to-nationwide rollout timeline — see the two-part tariff anchor page →.

Worked example: a 6 MW third-party colocation facility in Ho Chi Minh City

Representative scenario

Third-party colocation operator, 22 kV connection, post-Circular 60 commercial tariff

Setup

  • Facility typeThird-party colocation, ~6 MW IT load + 2 MW cooling/overhead, HCMC metro
  • Voltage22 kV connection
  • Tariff classificationBusiness (kinh doanh) per Circular 60/2025, effective December 2025
  • Monthly consumption~5,760,000 kWh (8 MW × 30 × 24)
  • Load profileNear-flat IT, +15% afternoon cooling peak; 60/35/5 normal/peak/off-peak split
  • Registered Pmax9,500 kW pre-BESS (N+1 redundancy reservation); 9,000 kW post-BESS (500 kW cooling peak shave)
  • BESS under consideration2 MW / 8 MWh behind-the-meter, arbitrage + afternoon cooling-peak shave

Monthly bill comparison (VND millions, current FX)

Component Today — single-part, business tariff Pilot — if scoped in, no BESS Pilot — if scoped in, with BESS
Peak energy (~2,016,000 kWh) 10,130 4,448 4,448
Standard energy (~3,456,000 kWh) 9,977 4,467 4,467
Off-peak energy (~288,000 kWh) 463 252 252
Energy sub-total 20,570 9,167 9,167
Capacity charge (Pmax × VND 235,414) 2,236 2,119
Total monthly bill 20,570 11,403 11,286
Delta vs today baseline −44.6% −45.1%

What the numbers say

The apparent 44% bill reduction is almost entirely explained by the shift from business-tariff energy rates (~VND 5,025 peak, 1,609 off-peak) to pilot energy rates (roughly VND 2,200 peak, 870 off-peak). That shift assumes the pilot applies to this third-party facility — which is the scope question flagged in §3. If MOIT confirms third-party data centres are excluded, the "Pilot" columns are hypothetical; the facility stays on the full business tariff and Circular 60's cost shock is permanent.

The BESS layer, if the facility is in the pilot, saves only ~VND 117 million per month from Pmax reduction — approximately USD 4,600/month or USD 55,000/year. That is real money but it is not the main economic driver. The arbitrage revenue from the same 2 MW / 8 MWh BESS, cycling once daily, adds a separate stream worth roughly USD 13,000–15,000/month at compressed pilot spreads. For a USD 380,000 BESS (~USD 190/kWh × 8,000 kWh × 0.25 utilisation for arbitrage-only dispatch — revise using the BESS calculator), the payback lands around 3 years inclusive of capacity and arbitrage revenue.

In practice: the operator's BESS business case on this site should not rely on capacity-charge saving as the headline number. Arbitrage + backup-value displacement (avoiding UPS battery refresh CAPEX) are the defensible economics. Capacity saving is a welcome layer if the pilot applies, and evaporates if it doesn't.

Source: Arcus Energy indicative scenario combining Decision 1279/QĐ-BCT business tariff rates (22 kV, May 2025), EVN two-part tariff pilot documentation (VND 235,414/kW/month; midpoint of published ranges for energy rates), and a load profile representative of a mid-sized HCMC colocation operator. Not a live project; numbers rounded to the nearest VND 1 million.

Frequently asked questions

Are data centres in the July 2026 two-part tariff pilot?

It depends on classification. A captive data centre sitting on the manufacturing tariff, consuming ≥200,000 kWh/month at ≥22 kV, is clearly in — Decree 146 and EVN's pilot documentation both confirm the scope. A third-party (colocation or hyperscale-lease) data centre moved onto the commercial tariff by Circular 60/2025 sits in genuinely uncertain scope because the pilot was framed against the "manufacturing customer" universe before Circular 60 reclassified most commercial data centres out of it. MOIT has not clarified the interaction publicly as of April 2026.

Does the two-part tariff reverse the Circular 60 advantage for captive data centres?

No. The captive advantage narrows but does not reverse. Under Circular 60/2025 the captive data centre kept the cheaper manufacturing tariff — a ~45–55% blended-cost saving versus third-party. Under the two-part pilot the captive faces arbitrage-spread compression with little peak-shaving offset because captive load is typically flat, reducing the saving. A reasonable directional estimate on Arcus's working assumptions is that the captive-versus-third-party gap closes by 5–10 percentage points once the two-part tariff activates; the captive still pays materially less overall.

Why does data-centre load profile make the two-part tariff a worse deal than for factories?

The two-part tariff is designed to reward flat load. A customer whose demand barely varies from midnight to midnight comes out ahead because the capacity charge is matched by higher effective utilisation. A factory with a short peaky shift pattern can use BESS to shave 15–20% off registered maximum demand and capture a direct capacity-charge saving. Data centres fall on the wrong side of this logic: their IT load is near-flat (good) but their cooling overhead creates a predictable afternoon peak that BESS cannot economically reshape, and N+1 redundancy forces them to declare a higher Pmax than they ever actually draw. The result is a capacity charge that is hard to reduce.

What should a Vietnamese data-centre operator do before July 2026?

Three steps. First, confirm tariff classification under Circular 60/2025 — captive, third-party, or mixed — because this determines pilot scope. Second, file a formal inquiry with your EVN regional corporation about two-part tariff pilot status; get the answer in writing before 1 July 2026 so any contract negotiations reference a confirmed position. Third, model both the current single-part bill and the two-part pilot bill side-by-side using actual site load data — pay particular attention to the Pmax declaration because this is the single most consequential decision in the pilot onboarding process.

If my data centre is on a DPPA under Decree 57, how does the two-part tariff affect me?

Double-charging risk. The Decree 57 grid-connected DPPA charges a CDPPA grid service fee; the two-part tariff charges a capacity fee; both recover grid-infrastructure costs through different mechanisms with no netting specified in either regulation. Norton Rose Fulbright's January 2026 commentary confirmed DPPA offtakers will likely still pay the full capacity charge. An amending decree to Decree 57 is expected in Q2–Q3 2026 to resolve the overlap. Until then, any DPPA term sheet signed by a data centre in the pilot cohort should include a specific change-in-law clause addressing the double-charging exposure.

What size BESS makes sense for a data centre under the two-part tariff?

Smaller than for a factory of equivalent load. At a factory the BESS is sized to capture both arbitrage (peak discharge, off-peak charge) and capacity-charge reduction (Pmax shaving) — typically 15–20% of connected load. At a data centre the peak-shaving opportunity is structurally limited because IT load is flat and cooling peaks are predictable, so BESS sizing shifts toward arbitrage-only economics combined with backup-value. For Arcus's typical 22 kV third-party DC scenario, a 1–2 MW / 2–4 MWh BESS focused on 4-hour peak discharge and UPS displacement is more defensible than an aggressively peak-shaving design.

Last updated · 24 April 2026 (fourteenth session, Pattern D spoke build) Canonical URL · arcusenergyasia.com/resources/regulations/two-part-tariff/for-data-centres