Circular 62 for data centres: what Vietnam's BESS pricing framework means for your facility
The short answer — Circular 62 does not directly govern behind-the-meter BESS at a data centre. But it reshapes three things a data-centre operator in Vietnam should care about.
Page current as of 22 April 2026. Anchor regulation: Circular 62/2025/TT-BCT, effective 26 January 2026. See the full Circular 62 explainer.
Does Circular 62 apply to my data centre?
No, Circular 62 does not apply to a typical data centre's BESS installation. Circular 62 governs standalone grid-connected battery energy storage systems that sell power to the national grid, not batteries installed behind the customer's meter for peak-shaving, backup, or arbitrage.
Circular 62's scope is explicit and narrow. A project must meet three cumulative conditions to fall under the regulation:
- Standalone — the BESS is its own asset, not integrated with a renewable generation plant (Circular 12/2025/TT-BCT covers that) and not owned by a Power Corporation (Circular 17/2025/TT-BCT covers that)
- Grid-connected — the BESS supplies power to the national grid via a PPA with EVN, a Power Corporation, or (in future) a wholesale-market offtaker
- Scale thresholds — 10 MW or more capacity AND 110 kV or higher grid connection voltage, AND developed under the revised Power Development Plan VIII (Decision 768/QĐ-TTg, April 2025)
A behind-the-meter BESS at a data-centre site fails two of these three on most projects: it is rarely connected at 110 kV, and it is not selling power to the grid — it is displacing grid imports for the customer's own consumption. Even a 10+ MW behind-the-meter BESS at a hyperscale campus remains out of scope because the power never leaves the customer's electrical boundary.
In practice: the regulation that governs behind-the-meter BESS at a data-centre site is the retail-tariff regime — Decision 1279/QĐ-BCT sets the VND/kWh rates, and Decree 146/2025/NĐ-CP will add a capacity charge for the largest customers from the 2028–2030 rollout.
Why Circular 62 still matters to data-centre strategy
Three indirect but material channels. The anchor page describes Circular 62 as wholesale-market infrastructure; this section describes what that infrastructure does for a data-centre operator.
4.1 · Grid stability and renewable integration
Vietnam's revised Power Development Plan VIII targets 10,000–16,300 MW of BESS by 2030, a roughly 40-fold increase on the original plan. That target is only achievable if BESS investors have bankable unit economics — which is what Circular 62 provides. The deployment of standalone utility-scale BESS at this scale directly supports grid stability in ways that matter to a data centre:
- Curtailment relief — the renewable generation that a data centre's Scope 2 reporting depends on (via DPPA or via commercial sourcing claims) is today routinely curtailed at 15–30% in high-penetration provinces like Ninh Thuan. Standalone BESS absorbs this curtailed energy and dispatches it later, restoring the renewable output that would otherwise be lost.
- Frequency regulation — utility-scale BESS provides sub-second frequency response that the existing thermal-heavy fleet cannot match. Data-centre load is particularly sensitive to frequency deviations; BESS-supported grids are measurably more stable.
- Peak reliability — evening peak reliability in Ho Chi Minh City, Binh Duong, Dong Nai, and the northern manufacturing belt — the provinces where most Vietnamese data centres are sited — has been under pressure for three years. The 10,000–16,300 MW BESS build-out is the primary planned mitigation.
In practice: a data centre evaluating a 10–15 year site lease in 2026 should view Circular 62 as the regulatory mechanism that makes Vietnam's grid incrementally more reliable over the lease term. This is not a direct project ROI input but a real site-selection factor for hyperscale buyers.
4.2 · Virtual PPA pathways with standalone BESS projects
Decree 57/2025/ND-CP governs direct power purchase agreements between renewable generators and large consumers. Circular 62 governs standalone grid-connected BESS. The intersection — a data centre signing a virtual PPA with a solar+BESS or wind+BESS project where the BESS element is a Circular-62-compliant standalone asset — is not yet operational because the amending decree to Decree 57 (expected Q2–Q3 2026) has not been issued, and the implementation of Resolution 253/2025 free-price negotiation is still in consultation.
But the mechanism is commercially useful and legally possible under the two regulations read together. Three configurations are already being explored by corporate offtakers:
- Solar-paired BESS under a single DPPA — the BESS is co-located with a solar plant, governed by Circular 12/2025/TT-BCT, and the offtake is a single DPPA under Decree 57. This is the dominant near-term configuration and is not Circular 62 scope.
- Standalone BESS as capacity-firming backstop — the data centre signs a primary DPPA with a solar or wind plant, and a secondary contract with a standalone Circular-62 BESS project that firms up the intermittent generation. Two offtake contracts, two regulatory regimes.
- Pure virtual PPA with standalone BESS — purely financial; the data centre pays the BESS owner a contract for differences against a reference price, with no physical power flow between them. Likely the first configuration to reach precedent once Resolution 253 implementation resolves.
In practice: none of these configurations is contractable today in a clean form. All three are likely contractable by end-2026 as the Decree 57 amending decree issues and Circular 62's first annual price bracket is approved. Data centres with corporate 100% RE commitments should structure their 2026 procurement strategy to allow for these pathways as they become operational, rather than assuming a single bilateral DPPA is the only route.
4.3 · Circular 60 reclassification reinforcement
Circular 60/2025/TT-BCT reclassified third-party data centres from the manufacturing tariff to the commercial (kinh doanh) tariff effective 2 December 2025 — a 45–55% increase in blended electricity cost for most operators. That reclassification is not Circular 62 territory, but the two regulations interact in a useful way for data-centre strategy.
Under the commercial tariff at 22 kV, the peak-to-off-peak spread is VND 3,416/kWh versus VND 2,208/kWh on the manufacturing tariff — 55% wider. This makes behind-the-meter BESS at a data-centre site more economically valuable than at a manufacturing site. Circular 62 doesn't govern that behind-the-meter BESS, but the broader PDP8-revised policy logic that produced Circular 62 (grid flexibility, cost-reflective pricing, renewable-integration infrastructure) also produced Circular 60. The regulator's direction of travel is consistent: reward customers who can flatten their load profile, penalise those who cannot.
In practice: the intelligent data-centre investment response to Circular 60 is behind-the-meter BESS sized to capture the commercial-tariff peak-to-off-peak spread. That is governed by Decision 1279 and Decree 146, not Circular 62. But the political and regulatory conditions that make that BESS investment worthwhile were all created by the same PDP8-revised policy framework that produced Circular 62.
Circular 62 terms most relevant to data-centre operators
Keeping this brief per the <20% overlap discipline. The anchor page covers the full framework — this section calls out specifically what a data-centre operator or procurement team needs to know when encountering Circular 62 in counterparty diligence, site selection, or corporate-RE strategy.
- The 12% IRR cap constrains standalone BESS project returns. If a data centre is evaluating a virtual PPA or contract-for-differences with a Circular 62 project, this cap is the structural ceiling on what the counterparty can earn — which in turn bounds what the data centre can negotiate on strike price.
- Annual price bracket approval is a new administrative process running for the first time in late 2026. Counterparties you may sign long-term contracts with will be operating against a pricing envelope that has no implementation precedent, which is a material contract-risk factor worth addressing through change-in-law clauses.
- FX adjustment mechanism in the regulated PPA applies to capacity and energy payments. Because data-centre procurement contracts are often USD-denominated internally while the BESS PPA is VND-denominated, understanding how Circular 62's FX adjustment propagates is relevant to any hedge strategy.
- Dispatch rules are not fully specified in the Circular itself and will be developed through operational guidance. Until that guidance issues, the energy-payment volume a Circular 62 BESS can expect is uncertain — which translates to uncertainty on any energy-linked virtual PPA a data centre might sign.
For the full regulatory text explanation — Article 5 (Average Fixed Price), Article 7 (Fixed O&M Price), the Variable Price charging-cost methodology, PPA mandatory contents, exclusions — see the Circular 62 anchor page →.
Worked example: a 30 MW hyperscale data centre in Long An evaluates Scope 2 strategy
Scope check across a data centre's BESS footprint
Setup
- IT load30 MW hyperscale data centre, Long An province
- Annual consumption~263 GWh (30 MW × 8,760 hours × ~95% utilisation)
- Voltage22 kV connection (typical for a 30 MW site not yet justifying a 110 kV direct connection)
- Tariff classificationThird-party commercial (kinh doanh) per Circular 60/2025
- Corporate commitment100% renewable electricity by 2030 (hyperscale industry baseline)
- BESS under consideration10 MW / 40 MWh behind-the-meter, for peak-shaving and backup
Regulatory scope check
| Question | Answer | Regulation |
|---|---|---|
| Does Circular 62 govern the 10 MW / 40 MWh behind-the-meter BESS? | No — it's behind-the-meter, not standalone | Decision 1279 + Decree 146 |
| If we sign a DPPA with a 50 MW solar + 20 MWh BESS, which regulation applies to the BESS? | Circular 12/2025/TT-BCT — BESS is co-located with RE | Not Circular 62 |
| If we sign a contract for differences with a 100 MW standalone BESS in Ninh Thuan, which regulation applies? | Circular 62 — the BESS is standalone, grid-connected, meets thresholds | Circular 62 |
| Does the Circular 60 commercial tariff classification interact with any of this? | Yes — it makes behind-the-meter BESS more valuable by widening the arbitrage spread | Decision 1279 |
Commercial implications
The direct BESS investment at the data centre site is governed by the retail tariff regime — the customer pays VND 5,025/kWh peak at 22 kV commercial, and behind-the-meter BESS captures a VND 3,416/kWh peak-to-off-peak spread. Circular 62 has zero direct role in that investment decision.
The Scope 2 strategy, however, is where Circular 62 enters. The data centre's 2030 100%-RE commitment requires contracted renewable supply at scale — in this case approximately 263 GWh/year. That supply will come through a portfolio approach: a DPPA with a solar project (governed by Decree 57 + Circular 12 for the co-located BESS), potentially a second DPPA with a wind project, and potentially a financial CfD with a standalone BESS project that firms up the intermittent generation during evening peak and outages (governed by Circular 62 once the amending decree clarifies the pathway).
In practice: the data-centre operator's engagement with Circular 62 is not "does this regulation apply to my site BESS" (answer: no) but "how does this regulation reshape the menu of contracted renewable supply options I can use to meet my 2030 commitment" (answer: it opens standalone BESS as a capacity-firming counterparty, pending amending-decree resolution).
Source: Arcus Energy indicative scenario illustrating regulatory scope, not a live project.
Frequently asked questions
Does Circular 62/2025 apply to behind-the-meter BESS at a data centre?
No. Circular 62 applies only to standalone grid-connected BESS of 10 MW or more at 110 kV or higher, developed under PDP8 revised. A behind-the-meter BESS installed at a data-centre site is governed by the retail-tariff regime — Decision 1279/QĐ-BCT for the commercial tariff today, plus Decree 146/2025/NĐ-CP two-part tariff once it extends to commercial customers.
My data centre is considering a 10 MW on-site BESS. Does Circular 62 apply?
No — the 10 MW capacity threshold on its own is not sufficient. Circular 62 requires cumulative conditions: standalone, grid-connected, ≥10 MW, ≥110 kV, and under PDP8 revised. A 10 MW on-site BESS at a data centre site is behind-the-meter, typically at 22 kV, and does not sell power to the grid — so it fails the standalone and grid-connected tests.
Can my data centre sign a PPA with a standalone BESS project?
In principle yes, through a virtual PPA or contract for differences, once Decree 57's amending implementing decree issues (expected Q2–Q3 2026) and Resolution 253/2025 free-price negotiation is operational. A standalone BESS under Circular 62 is a valid RE-adjacent counterparty for a corporate offtaker with a 100%-renewable commitment, though the contract structure is not yet mature in the Vietnamese market.
How does Circular 62 interact with the Circular 60 data-centre reclassification?
They are different regulations addressing different things — Circular 60 reclassifies third-party data centres into the commercial tariff bracket, raising their blended electricity cost; Circular 62 sets the BESS pricing framework that supports grid-stability investments. Both reflect the same PDP8-revised policy direction: cost-reflective pricing and grid-flexibility infrastructure.
Will the 12% IRR cap under Circular 62 affect the price I pay for renewable power under a virtual PPA?
Yes, indirectly. The 12% IRR cap constrains what a standalone BESS counterparty can earn — which in turn constrains the floor under any strike price negotiation. If a data centre is signing a contract for differences with a Circular 62 BESS project, expect the counterparty to negotiate toward a price that preserves their regulated return; the cap is a real constraint on commercial flexibility.
Should my data centre wait for Circular 62 implementation to mature before committing to BESS strategy?
No. Behind-the-meter BESS at the site is governed by Decision 1279 and Decree 146, not Circular 62, and those frameworks are already operational. Circular 62 affects the menu of off-site contracting options (virtual PPA with standalone BESS, capacity-firming CfDs) — wait only if those are on your critical path for a 2026–2027 procurement decision.