Regulation · Pilot begins July 2026

The two-part tariff: Vietnam's capacity + energy pricing reform

Vietnam's retail electricity tariff is being restructured to add a capacity charge (VND/kW/month) alongside the existing energy charge. Legal basis: Decree 146/2025/NĐ-CP and Article 50 of the amended Electricity Law 2024.

Status: Parallel shadow billing since 1 January 2026 for ~7,000 large manufacturers. Real-money billing from 1 July 2026. Nationwide rollout from 2028. This page last updated: 23 April 2026.

Key facts

Legal basisArticle 50 of the amended Electricity Law 2024 (Law 61/2024/QH15), implemented by Decree 146/2025/NĐ-CP
Pilot shadow billingFrom 1 January 2026 (parallel invoicing, no commercial effect)
Pilot real billingFrom 1 July 2026
Pilot end date31 July 2027 (evaluation period, nationwide expansion follows)
Pilot scopeApproximately 7,000 manufacturing customers ≥200,000 kWh/month at ≥22 kV
StructureCapacity charge (VND/kW/month, based on registered Pmax) + energy charge (VND/kWh by TOU band)
Capacity charge rangeVND 209,459/kW/month (≥110 kV) to VND 286,153/kW/month (<6 kV)
Nationwide rolloutExpected 2028–2030
Related regulationsDecree 57/2025/ND-CP (DPPA — double-charging overlap); Circular 60/2025/TT-BCT (TOU framework); Circular 62/2025/TT-BCT (standalone BESS two-part pricing); Decree 72/2025/NĐ-CP (retail price adjustment mechanism)

What the two-part tariff actually does

What is the two-part tariff and how does it differ from today's electricity bill?

Direct answer. The two-part tariff replaces Vietnam's single-part (energy-only) retail bill with a two-component bill: a fixed capacity charge based on registered maximum demand, plus a variable energy charge billed by time-of-use band. The total bill has the same underlying cost recovery — but it is redistributed to reward flat load profiles and penalise peaky consumption.

Under today's tariff structure (Decision 1279/QĐ-BCT), a 22 kV manufacturing customer pays a single VND/kWh rate that varies by time-of-use band: peak 3,398 VND/kWh, standard 1,833 VND/kWh, off-peak 1,190 VND/kWh. Under the two-part tariff, that customer pays two separate charges each month. The first is a capacity charge calculated as registered maximum demand (in kilowatts) multiplied by a fixed VND/kW/month rate — for 22 kV manufacturing, VND 235,414/kW/month. The second is an energy charge billed by TOU band, at new rates roughly 30–35% below today's energy-only rates, because part of grid-cost recovery has moved from the per-kWh charge to the per-kW capacity charge. The customer pays the capacity fee every month regardless of consumption; if they shut down for a month, the capacity bill is unchanged, but the energy bill drops to zero.

In practice: the customer most exposed to the new structure is the one with a short, spiky peak — a factory that runs three shifts one week per month but is otherwise idle, or a data centre with large redundant-capacity reservations. The customer most rewarded is the one running a flat, high-utilisation load. BESS peak-shaving sits directly on top of this: every kW shaved from registered maximum demand cuts the monthly capacity bill permanently.

Who is in the pilot and who is excluded?

Direct answer. The pilot covers approximately 7,000 manufacturing customers consuming an average of ≥200,000 kWh per month at voltage ≥22 kV — the same eligibility universe as Decree 57's grid-connected DPPA. Hospitality, commercial, retail, and sub-22-kV customers are excluded from the pilot.

The 200,000 kWh/month threshold excludes most hotels, restaurants, and SMEs. It includes mid-to-large factories and every hyperscale data centre. EVN has publicly confirmed the pilot cohort figure; MOIT's implementation guidance extends the threshold logic by requiring TOU-capable metering for all producers and businesses with transformers ≥25 kVA or monthly consumption ≥2,000 kWh under Circular 60/2025/TT-BCT — a separate but parallel workstream that prepares the broader customer base for eventual rollout. A customer just below the pilot threshold today (say, 180,000 kWh/month) will not enter real billing in July 2026 but will enter the nationwide expansion from 2028. Customers connected at under 22 kV fall outside the pilot regardless of consumption.

In practice: for most Arcus prospects, the question is not "am I in the pilot" but "when does this apply to me." Factories above ~2 MW connected load at 22 kV+ are typically in. Every commercial-scale data centre is in from day one. Hotels and commercial sites are out of the pilot but should model the structure now — they will enter during the 2028–2030 rollout and the commercial tariff has the widest peak/off-peak spread in Vietnam, making the economics most sensitive there.

How does the capacity charge work in practice?

Direct answer. The customer declares a registered maximum demand figure (Pmax) in kilowatts when entering the pilot. Each month, the customer is billed Pmax × the VND/kW/month rate for their voltage band, regardless of whether they actually hit that peak during the month.

Pmax is measured in kilowatts over a rolling window — typically a 15- or 30-minute sliding average at the high-tension meter. The customer agrees a declared Pmax figure with their EVN regional corporation when joining the pilot; if the customer exceeds declared Pmax in a given month, penalty charges apply. If the customer consistently undershoots, they can renegotiate Pmax downward at agreed review points. The capacity charge rate by voltage band, from EVN's pilot documentation:

Voltage bandCapacity rate (VND/kW/month)
≥ 110 kV209,459
22 kV to < 110 kV235,414
6 kV to < 22 kV240,050
< 6 kV286,153

The structural logic is cost-reflective: higher-voltage connections use more proximate grid infrastructure and fewer downstream transformation stages, so their capacity charge is lower per kW. Sub-6 kV connections at the tail of the distribution system bear the highest per-kW capacity cost.

In practice: the capacity charge creates a strong incentive to shave peaks and declare a lower Pmax. A factory registering Pmax at 2,000 kW at 22 kV pays VND 471 million per month in capacity charges alone (USD ≈18,500 at April 2026 FX). Cutting Pmax to 1,500 kW through BESS peak-shaving saves VND 118 million per month — approximately USD 4,600 per month, USD 55,000 per year, for every 500 kW of Pmax reduction.

What happens to the energy charge?

Direct answer. Under the pilot, the energy charge falls by approximately 30–35% versus today's Decision 1279 rates — because part of grid-cost recovery has moved to the new capacity component. The TOU band structure (peak, standard, off-peak) is retained.

EVN's pilot documentation shows draft pilot energy rates of VND 843–904/kWh off-peak, VND 1,253–1,332/kWh standard, and VND 2,162–2,251/kWh peak, with the exact number within each range depending on voltage band. Compared with Decision 1279's 22 kV manufacturing rates of VND 1,190 off-peak, VND 1,833 standard, VND 3,398 peak, the pilot rates represent a ~25–35% reduction in the variable bill component. The peak–off-peak arbitrage spread therefore narrows from VND 2,208/kWh under today's structure to roughly VND 1,300–1,400/kWh under the pilot — a compression of ~35–40%.

In practice: this is the single most important structural effect for BESS business cases. The energy arbitrage revenue (peak minus off-peak, adjusted for round-trip efficiency) falls by roughly a third under the pilot. But that revenue loss is more than offset by the capacity-charge saving from peak-shaving, provided the customer has a peaky load that can actually be shaved. A flat baseload data centre gains little from peak-shaving; a batch-manufacturing factory with sharp demand spikes can gain substantially more than it loses on arbitrage compression.

How does this interact with DPPA and the new TOU windows?

Direct answer. Decree 57 DPPA offtakers face a potential double-charging risk because both the new capacity charge and the CDPPA grid service charge under Decree 57 recover grid-infrastructure costs. MOIT's separate April 2026 consultation on new TOU windows will reshape when capacity-reducing peak-shaving is most valuable.

Norton Rose Fulbright confirmed in January 2026 commentary that DPPA offtakers under Decree 57 Model 2 (grid-connected) will likely still pay the full capacity charge to EVN — the CDPPA charge recovers similar grid costs through a different mechanism, but there is no netting specified in either regulation. An amending decree to Decree 57 is expected in 2026 to resolve the overlap; until then, any DPPA term sheet signed under the pilot cohort should include a change-in-law clause specifically addressing the double-charging risk. Separately, MOIT published a public consultation draft on 15 April 2026 proposing new TOU windows under Circular 60/2025/TT-BCT — both the MOIT seasonal proposal and EVN's counter-proposal eliminate the 09:30–11:30 morning peak. If the EVN proposal (single 17:30–22:30 evening peak) is adopted, BESS peak-shaving becomes more valuable because the current split peak (2 hours morning + 3 hours evening) consolidates into a continuous 5-hour evening block — the total peak hours stay the same, but a single longer discharge cycle is more efficient than two shorter ones and removes the morning ramp-down cost.

In practice: any project modelling two-part tariff economics in 2026 should do so against three scenarios — current TOU, MOIT seasonal proposal, EVN evening-only proposal. The hybrid solar + BESS configuration wins under all three, but the exact payback delta shifts with which TOU regime is adopted. Watch for the MOIT final decision in Q3 2026.

Timeline

30 November 2024 Issued Electricity Law 61/2024/QH15 passes; Article 50 provides the statutory basis for two-component retail pricing. National Assembly
1 February 2025 Effective Electricity Law 61/2024/QH15 takes effect, replacing the 2004 Electricity Law in full. National Assembly
28 March 2025 Issued Decree 72/2025/NĐ-CP rewrites the retail price adjustment mechanism, lowering the trigger threshold to 2%. Government of Vietnam
Mid-2025 Issued Decree 146/2025/NĐ-CP published, implementing Article 50 and defining the two-part tariff structure, pilot scope, and capacity-charge rate grid. Government of Vietnam
20 August 2025 Issued Politburo Resolution 70-NQ/TW on national energy security commits to cost-reflective pricing, providing the political mandate for two-part tariff rollout. Central Committee
October 2025 Milestone EVN begins shadow-parameter testing with the pilot cohort; Pmax declarations registered. EVN
1 January 2026 Shadow billing Parallel shadow invoices issued to approximately 7,000 pilot cohort customers; no commercial effect. EVN
26 January 2026 Effective Circular 62/2025/TT-BCT takes effect; standalone BESS ≥10 MW at ≥110 kV uses its own two-part capacity+energy structure separately from the retail pilot. MOIT
15 April 2026 Consultation MOIT publishes public consultation draft on new TOU peak-hour windows under Circular 60/2025; EVN counter-proposal on record. MOIT
1 July 2026 Pending Two-part tariff enters commercial effect for the pilot cohort — real-money billing begins. EVN, expected
Q2–Q3 2026 Pending Amending decree to Decree 57 expected; scope includes CDPPA / capacity-charge double-charging resolution. Government of Vietnam, expected
31 July 2027 Pending Formal pilot evaluation period ends; nationwide expansion criteria finalised. EVN, expected
August 2027 Pending Broader rollout begins beyond the 7,000 pilot customers. EVN, expected
2028–2030 Pending Two-part tariff becomes the default retail structure for eligible C&I customers nationwide. Government of Vietnam, expected

Articles and thresholds

Article 50 · Electricity Law 61/2024/QH15

Electricity price structure

Article 50 establishes the statutory basis for a two-component retail tariff comprising a capacity charge and an energy charge. It authorises the Government to set the applicable customer categories, voltage bands, and phased rollout through implementing decrees — which is what Decree 146/2025/NĐ-CP then does. The Law does not itself fix rates or timings.

In practice: the Law creates the structure; the Decree fills it in. This two-level design means Decree 146 can be amended faster than the Law itself if pilot data warrants rate or scope changes.

Decree 146/2025/NĐ-CP

Implementation of the two-part tariff

Decree 146 defines the pilot cohort (manufacturing customers ≥200,000 kWh/month at ≥22 kV), sets the capacity charge rate grid by voltage band, specifies the Pmax declaration and true-up mechanism, and establishes the parallel shadow billing and real-money billing dates. It assigns MOIT the authority to issue detailed guidance on metering, registration, and dispute resolution.

In practice: the Decree text is the binding reference for any project-finance lender or counterparty evaluating a two-part tariff exposure. Obtain the official Vietnamese text from vbpl.vn rather than relying on English summaries for contractual language.

Circular 60/2025/TT-BCT

TOU framework — interaction

Circular 60 is the operative TOU framework that the two-part tariff's energy component is billed under. Its provisions on TOU metering mandate (transformers ≥25 kVA or ≥2,000 kWh/month) create the metering infrastructure that the two-part tariff's Pmax measurement also depends on. The two regulations operate in parallel and are designed to be mutually reinforcing.

In practice: any customer entering the two-part tariff pilot already has TOU-compliant metering from Circular 60. The reverse is not true — many customers with TOU meters do not meet the two-part tariff pilot threshold, but will as the rollout expands.

Circular 62/2025/TT-BCT

Standalone BESS — adjacent regulation

Circular 62 applies a conceptually similar capacity + energy pricing structure to standalone grid-connected BESS projects ≥10 MW at ≥110 kV, with an IRR cap of 12% and CPI+2.5% escalation. The two frameworks are legally distinct: Circular 62 governs what BESS owners receive from EVN for grid services; Decree 146 governs what retail customers pay to EVN for their supply. Projects combining behind-the-meter BESS at a two-part-tariff customer site interact with Decree 146, not Circular 62.

In practice: a C&I customer signing a BESS lease or EPC contract under a Decree 146 pilot site should confirm which regulation governs each revenue stream — arbitrage and capacity-saving are billed against Decree 146; any grid service export would fall under Circular 62's scope if scale thresholds are met.

Decree 72/2025/NĐ-CP

Retail price adjustment — mechanism interaction

Decree 72 sets the retail electricity price adjustment cadence and triggers. A draft amendment submitted in late 2025 would permit EVN to allocate approximately VND 44,792 billion of unrecovered 2022–2024 costs into the tariff, plausibly producing a 5–10% average retail-price uplift in Q2–Q3 2026. Any such uplift applies proportionally to both components of the two-part tariff.

In practice: the peak energy rate rises more in absolute VND/kWh than the off-peak rate under a percentage uplift, so the peak–off-peak arbitrage spread widens under the amendment even though the structure stays the same. The floor under BESS economics is regulation; the ceiling rises with tariff adjustments.

Commercial implications

The two-part tariff is the first material restructuring of Vietnam's retail electricity pricing since time-of-use bands were introduced in 2014. It arrives at the pilot cohort from 1 July 2026 and reshapes three things simultaneously: the composition of the monthly bill, the economics of behind-the-meter BESS, and the contractual risk profile of any DPPA signed under Decree 57. For Arcus's pipeline specifically, it accelerates the commercial case for hybrid solar + BESS on factory and data-centre sites while introducing a new negotiation item on every Model 2 DPPA term sheet.

  • For factories Every mid-to-large manufacturer ≥200,000 kWh/month at ≥22 kV is in the pilot from July 2026. The capacity charge at 22 kV manufacturing (VND 235,414/kW/month) creates a direct monetisable return for BESS peak-shaving — separate from, and additive to, energy arbitrage. Pitch decks for manufacturing clients should model the dual revenue stack. See how this applies to factories → · Two-part tariff for factories →
  • For data centres Hyperscale and third-party data centres above the threshold are all in the pilot. The reclassification into the commercial (kinh doanh) tariff under Circular 60/2025 already raised their blended rate by ~45–55%; the two-part tariff then reshapes how that higher bill is composed. For data centres running flat load profiles the capacity-charge impact is large and the peak-shaving opportunity limited, so BESS economics rely more on outage-backup and site-resilience value than on peak-shaving. See how this applies to data centres → · Two-part tariff for data centres →
  • For hotels Not in the pilot. Hospitality is excluded from the 2026–2027 scope because few individual hotels consume ≥200,000 kWh/month even when large. But the commercial (kinh doanh) tariff bracket that hotels sit in has the widest peak–off-peak spread in Vietnam, and Politburo Resolution 70 points to cost-reflective pricing across the commercial sector in the 2028–2030 rollout. Hotels planning BESS investment in 2026 should model the structure now so the return stands up under the broader rollout. See how this applies to hotels →

The two-part tariff is not a headline rate change and the base tariff remains Decision 1279/QĐ-BCT. What it does is reprice the grid-infrastructure component of every electricity bill against the structural shape of the customer's load. That shift — from paying per kWh to paying per declared kW plus per kWh — rewards the customer who can flatten their profile and penalises the one who cannot. BESS is the only proven technology for flattening C&I load profiles at scale, which is why the two-part tariff is the single most important regulatory development for Vietnam's BESS market in the decade since TOU was introduced.

Worked example

Worked example · 22 kV manufacturing, Binh Duong

A 2.4 GWh/month manufacturing facility under the two-part tariff

Setup

  • LocationManufacturing facility, Binh Duong province
  • Voltage22 kV
  • Consumption~2,400,000 kWh/month (well above the 200,000 kWh pilot threshold)
  • TOU split25% peak / 60% standard / 15% off-peak — typical three-shift profile
  • Pmax (no BESS)4,500 kW
  • Pmax (with BESS)3,800 kW (700 kW shaved via 700 kW / 1,400 kWh BESS)
  • ComparisonDecision 1279 (today) vs Decree 146 (pilot, with and without BESS)

Monthly bill — all figures VND millions

Component Today (1279) Pilot · no BESS Pilot · with BESS
Peak energy (600,000 kWh)2,0391,3241,324
Standard energy (1,440,000 kWh)2,6401,8611,861
Off-peak energy (360,000 kWh)428314314
Energy sub-total5,1073,5003,500
Capacity charge (Pmax × 235,414)1,059895
Total monthly bill5,1074,5594,394
Delta vs todaybaseline−10.7%−13.9%
Additional saving from BESS peak-shaving+165 / month

Under the pilot structure, this facility pays about 10.7% less than today even without any demand-side management — because the energy rate reduction more than offsets the new capacity charge at the facility's current load profile. With a 700 kW BESS sized to shave roughly 15% off registered Pmax, the customer saves an additional VND 165 million per month — approximately USD 6,500 monthly or USD 78,000 annually, from capacity-charge reduction alone. Energy arbitrage revenue on the same BESS adds a further stream whose size depends on the finalised pilot peak–off-peak spread. At an all-in BESS capex of USD 190/kWh (behind-the-meter C&I convention, April 2026), a 700 kW / 1,400 kWh BESS costs approximately USD 266,000; the capacity-charge-only payback is roughly 3.4 years, compressing further once energy arbitrage is layered in.

Source: Arcus Energy project analysis, anonymised; figures rounded. Rates referenced: Decision 1279/QĐ-BCT (May 2025), EVN pilot documentation via Arcus Energy Vietnam Tariff Briefing (April 2026). Pilot energy rates modelled at the midpoint of the VND 843–904, 1,253–1,332, 2,162–2,251 ranges reported by EVN.

Frequently asked questions

What is Vietnam's two-part tariff?

Vietnam's two-part tariff is a restructured retail electricity pricing model that splits the customer's monthly bill into two components — a capacity charge (VND/kW/month) based on registered maximum demand, and an energy charge (VND/kWh) billed by time-of-use band. The legal basis is Article 50 of Electricity Law 61/2024/QH15 and Decree 146/2025/NĐ-CP. The pilot begins real-money billing on 1 July 2026.

When does the two-part tariff start?

Parallel shadow billing has been live since 1 January 2026 for approximately 7,000 pilot-cohort manufacturing customers — they receive notional invoices showing what they would pay under the new structure, with no commercial effect. Real-money billing begins 1 July 2026 for the same pilot cohort. The formal pilot ends 31 July 2027, with nationwide expansion from August 2027 and broader rollout through 2028–2030.

Who is covered by the two-part tariff pilot?

The pilot covers approximately 7,000 manufacturing customers consuming on average ≥200,000 kWh per month at voltage ≥22 kV — the same eligibility threshold as Decree 57's grid-connected DPPA. Hotels, commercial customers, and sub-22-kV customers are excluded from the pilot. Most large factories and every hyperscale data centre are in.

What are the two-part tariff capacity charges by voltage?

Capacity charges under the pilot are VND 209,459/kW/month at ≥110 kV, VND 235,414/kW/month at 22 to <110 kV, VND 240,050/kW/month at 6 to <22 kV, and VND 286,153/kW/month at <6 kV. The rate is billed monthly on the customer's registered maximum demand (Pmax), regardless of actual consumption in the month.

Will my electricity bill go up or down under the two-part tariff?

It depends on load profile. Customers with flat, high-utilisation loads typically see a modest reduction because the energy-rate cut outweighs the new capacity charge. Customers with peaky, low-utilisation loads typically see an increase. BESS peak-shaving can shift a peaky customer from the first group to the second.

How does BESS save money under the two-part tariff?

BESS creates two distinct revenue streams under the two-part tariff. First, energy arbitrage — charging at off-peak rates and discharging at peak rates — continues as before, though the narrower energy-band spread under the pilot reduces this revenue by roughly a third. Second, peak-shaving cuts registered maximum demand (Pmax), which permanently reduces the monthly capacity charge at VND 235,414/kW/month for a 22 kV customer. The two revenue streams stack, and peak-shaving savings persist regardless of day-to-day dispatch.

How does the two-part tariff interact with Decree 57 DPPA?

Decree 57 grid-connected DPPA (Model 2) offtakers face a potential double-charging risk — both the two-part tariff capacity charge and the CDPPA grid service charge under Decree 57 recover grid-infrastructure costs through separate mechanisms, with no netting specified. Norton Rose Fulbright confirmed in January 2026 that DPPA offtakers will likely still pay the full capacity charge. An amending decree to Decree 57 is expected in 2026 to resolve the overlap.

When will the two-part tariff apply to hotels and commercial customers?

Hotels and commercial customers are excluded from the 1 July 2026 pilot scope. Based on EVN's stated rollout plan, nationwide expansion begins August 2027 and broader rollout through 2028–2030 is expected to extend the two-part tariff to the commercial (kinh doanh) tariff category. Politburo Resolution 70-NQ/TW, issued August 2025, provides the political mandate for cost-reflective pricing across all C&I segments.

Last updated · 23 April 2026 Canonical URL · arcusenergyasia.com/resources/regulations/two-part-tariff