Regulation · In force 26 January 2026

Circular 62/2025/TT-BCT: Vietnam's standalone BESS pricing framework

Vietnam's first formal pricing framework for standalone grid-connected battery energy storage, applying to systems ≥10 MW at ≥110 kV under the revised Power Development Plan VIII. Issued by MOIT on 10 December 2025.

Status: In force. Implementing legal basis: Electricity Law 61/2024/QH15 and Decree 40/2025/NĐ-CP. This page last updated: 23 April 2026.

Key facts

Issued10 December 2025 by MOIT
Effective26 January 2026
Legal basisElectricity Law 61/2024/QH15; Decree 40/2025/NĐ-CP; proposal of the Electricity Regulatory Authority
GovernsAnnual electricity generation price brackets and generation service prices for standalone grid-connected BESS; mandatory minimum contents of BESS Power Purchase Agreements
Scope thresholds≥10 MW capacity AND ≥110 kV grid connection voltage AND developed under PDP8 revised
Regulated entitiesStandalone BESS owners; EVN and its member Power Corporations; electricity system and market operators (including NSMO); offtake counterparties
Explicit exclusionsBESS co-located with renewable energy plants (governed by Circular 12/2025/TT-BCT); BESS owned by Power Corporations (governed by Circular 17/2025/TT-BCT); behind-the-meter C&I BESS (governed by Decision 1279 retail tariffs and Decree 146 two-part tariff)
Pricing ceilingMaximum price = Average Fixed Price (capex recovery) + Fixed O&M Price + Variable Price (charging cost recovery)
IRR cap12% pre-tax nominal WACC basis (structural to the Average Fixed Price formula)
EscalationO&M escalation CPI-linked, capped at +2.5% p.a.
Related regulationsElectricity Law 61/2024/QH15; Decree 40/2025/NĐ-CP; Decree 146/2025/NĐ-CP (two-part retail tariff); Decision 768/QĐ-TTg (PDP8 revised); Decision 1279/QĐ-BCT (retail tariff referenced for Variable Price calculation)

What Circular 62 actually does

What is Circular 62 and why does it matter?

Direct answer. Circular 62 is Vietnam's first legally binding pricing framework for standalone grid-connected battery energy storage. Before it took effect on 26 January 2026, there was no standardised mechanism for pricing power supplied by a BESS to the grid, which is the primary reason Vietnam's original PDP8 target of 300 MW of storage by 2030 produced zero deployed megawatts.

The revised Power Development Plan VIII, approved by the Prime Minister as Decision 768/QĐ-TTg in April 2025, raised the 2030 BESS target to between 10,000 MW and 16,300 MW — a roughly 40-fold increase over the original plan. A target at that scale is only credible if investors have predictable cash-flow terms, lenders have bankable PPAs, and offtakers have a transparent price ceiling. Circular 62 provides all three for the first time. It does not guarantee that deployment will happen at pace — implementation risks remain, including the annual price-bracket approval cycle and unresolved dispatch rules. What it does is convert Vietnam's BESS ambition from conceptual policy signalling into workable commercial machinery.

In practice: Norton Rose Fulbright's January 2026 commentary describes Circular 62 as the first standardised framework mechanism for pricing power supplied by large-scale BESS in Vietnam. That characterisation captures the function precisely — without Circular 62 the 10,000–16,300 MW target would be aspirational; with it, project-level commercial terms become negotiable.

What does the pricing framework actually look like?

Direct answer. Circular 62 establishes an annual electricity generation price bracket ranging from a minimum of 0 VND/kWh to a regulated maximum price. The maximum price is the sum of three components: an Average Fixed Price recovering investment capital, a Fixed Operation and Maintenance Price, and a Variable Price recovering the cost of charging electricity.

Each component is calculated under a defined methodology in the Circular. The Average Fixed Price (Article 5) is the annualised cost of construction investment capital divided by the expected average electricity delivered and received over the BESS's economic life — essentially a levelised-capex figure. The Fixed O&M Price (Article 7) covers major and minor repair costs, labour, and other recurring expenses, set as a VND/kWh component. The Variable Price recovers the cost of charging the BESS, calculated against (a) the BESS's self-consumption and transmission-loss rates during charging and (b) the off-peak retail tariff for manufacturing industries — which under the currently-in-force Decision 1279/QĐ-BCT is VND 1,190/kWh at 22 kV and VND 1,146/kWh at ≥110 kV.

The structural innovation is the dual-revenue treatment. BESS owners receive a Capacity Payment for grid availability independent of actual dispatch — stable cash flow that supports debt service — plus an Energy Payment for electricity actually delivered. This two-part structure mirrors mature-market designs (PJM, ERCOT, the UK capacity market) and is the first time any major ASEAN economy has adopted this model for storage.

In practice: the dual-revenue structure is the single most important feature for bankability. Lenders can underwrite the capacity payment as a contracted-revenue stream analogous to an availability-based PPA, which transforms the debt-service-cover calculation versus a pure energy-merchant asset.

Who is covered and who is excluded?

Direct answer. Circular 62 applies to owners of standalone grid-connected BESS projects meeting the 10 MW / 110 kV thresholds and developed under PDP8 revised, plus EVN, the power corporations, and the system and market operators as counterparties. It does not apply to BESS integrated with renewable power plants, BESS owned by the Power Corporations themselves, or any behind-the-meter C&I storage at a customer site.

The three exclusions matter commercially because they map onto three separate regulatory regimes. BESS integrated with renewable plants — the solar-plus-storage or wind-plus-storage configurations that dominate most new-build C&I projects — is governed by Circular 12/2025/TT-BCT, under which the BESS is treated as part of the generation plant rather than as a standalone asset. BESS owned by Power Corporations — meaning EVN subsidiaries deploying storage on their own accounts — is governed by Circular 17/2025/TT-BCT with its own cost-recovery framework. Behind-the-meter C&I BESS — factories, data centres, and commercial sites installing storage for peak-shaving and arbitrage — is not regulated as a generation asset at all; it interacts with the retail tariff under Decision 1279/QĐ-BCT and, from 1 July 2026 for large manufacturers, the two-part retail tariff under Decree 146/2025/NĐ-CP.

In practice: when advising a C&I client on a BESS investment, the first question is which regulation applies. Ninety-plus percent of Arcus's C&I pipeline sits under Decision 1279 + Decree 146 (retail) rather than Circular 62 (wholesale). Misapplying Circular 62 to a behind-the-meter project — which has happened in early 2026 pitch decks produced by other advisors — misleads the client on both revenue mechanism and approval process.

How is the price bracket approved and adjusted?

Direct answer. Each year before 1 November, EVN submits the proposed price bracket to the Electricity Regulatory Authority (ERA/ERAV, now the Electricity Department under MOIT), which appraises the submission and reports to the MOIT Minister for approval. Once approved, the bracket applies to PPAs negotiated in the following year. Individual project prices within the bracket are negotiated between the BESS owner and the offtake counterparty.

The investor's own workflow begins earlier: within 15 days of the project's feasibility study being approved, the investor must submit a completed pricing dossier to EVN. EVN aggregates across projects and submits to the Electricity Department under the 1 November deadline. The annual price bracket is published as a ceiling; actual contract prices within it are bilaterally negotiated, which introduces negotiating-position uncertainty that standalone BESS is particularly exposed to as a new asset class in Vietnam. The Circular includes detailed pricing, adjustment, and settlement formulas including a foreign-exchange adjustment mechanism — important because almost all BESS capex is imported and VND depreciation otherwise erodes project returns.

In practice: the annual approval cycle means any project reaching financial close in, say, Q2 of a given year will typically be negotiated against the price bracket approved in the prior November. First-mover projects negotiating in 2026 will be doing so against Circular 62's first-ever approved bracket, with limited precedent on where within the 0-to-ceiling range EVN will actually settle. Legal counsel should include change-in-law protection and benchmark-adjustment mechanisms in early-stage PPAs.

What are the open implementation questions?

Direct answer. Three significant implementation gaps remain despite Circular 62 being in force: the annual price-bracket review-and-approval process has no published precedent, operational dispatch arrangements are not fully specified in the Circular itself, and the interaction with Vietnam's evolving wholesale electricity market (VWEM) is still being worked out.

On the first point, the annual price-bracket approval is a new administrative process running for the first time in late 2026; investors and lenders have no historical reference on timing or decision logic. On the second, the Circular prescribes pricing and PPA contents but leaves dispatch scheduling, ancillary-service participation, and grid-integration rules to separate operational guidance. On the third, Circular 62 assumes offtake via EVN or the power corporations, but the longer-term direction of travel — following the broader electricity-market reform agenda — is toward wholesale-market participation. How a standalone BESS transitions from a bilateral PPA under Circular 62 to VWEM participation is not specified.

In practice: early project finance will price these implementation risks into return requirements, which is why the 12% IRR cap (pre-tax nominal WACC basis under Article 5) is tight for a new asset class. Expect the first tranche of Circular 62 projects to either (a) be anchored by strategic investors willing to accept the cap in exchange for first-mover positioning or (b) wait for the first annual approval cycle to produce implementation precedent before committing capital.

Timeline

30 November 2024 Issued Electricity Law 61/2024/QH15 passes; provides the statutory mandate under which Circular 62 is issued. National Assembly
1 February 2025 Effective Electricity Law 61/2024/QH15 takes effect. National Assembly
2025 Issued Decree 40/2025/NĐ-CP issued, the direct implementing decree under which Circular 62 is authorised. Government of Vietnam
April 2025 Issued Decision 768/QĐ-TTg approves PDP8 revised, raising 2030 BESS target from 300 MW to 10,000–16,300 MW and establishing the policy imperative for a BESS pricing framework. Prime Minister
10 December 2025 Issued Circular 62/2025/TT-BCT issued by MOIT, establishing Vietnam's first standardised BESS pricing framework. MOIT
26 January 2026 Effective Circular 62 takes effect. MOIT
Before 1 November 2026 Pending First annual price-bracket submission by EVN to the Electricity Department under MOIT; approval creates the first 2027 BESS pricing reference. EVN, expected
2026–2027 Pending First standalone BESS projects under Circular 62 expected to reach financial close, establishing implementation precedent. Industry, expected
By 2030 Pending PDP8 revised target of 10,000–16,300 MW BESS capacity deployed. Prime Minister, policy target

Articles and thresholds

Article 1 · Circular 62/2025/TT-BCT

Scope of regulation

Circular 62 regulates dossiers, sequences, and methods for determining and approving (a) the electricity generation price framework and (b) the electricity generation service price of battery energy storage systems meeting the defined scope. It also sets the main contents of the Power Purchase Agreement between BESS owner and offtaker.

In practice: the scope is deliberately narrow, leaving room for further circulars to cover adjacent BESS configurations that are not standalone, not grid-connected, or not within the PDP8 revised scope.

Article 2 · Circular 62/2025/TT-BCT

Applicable subjects

The Circular applies to agencies, organisations, and individuals owning BESS connected to the national power system at voltage ≥110 kV and capacity ≥10 MW, participating in the grid under PDP8 revised (2021–2030, vision to 2050). It also binds EVN and its member Power Corporations, the electricity system and market operators (including the National System and Market Operation Company, NSMO), and other relevant organisations.

In practice: the 110 kV / 10 MW thresholds deliberately target utility-scale deployment — the assets that materially affect grid reliability and renewable integration. Sub-threshold projects fall to behind-the-meter retail-tariff regimes or to the excluded categories above.

Article 5 · Circular 62/2025/TT-BCT

Average Fixed Price methodology

The Average Fixed Price is calculated as the annualised cost of construction investment capital (excluding VAT) divided by the average electricity delivered and received over the economic life of the BESS. The annualised capex incorporates the project's investment rate — the cost of bringing 1 kW of storage capacity online at the time of price-bracket calculation.

In practice: the economic-life assumption is the key modelling sensitivity. At a typical 15-year economic life and current LFP chemistry assumptions, the Average Fixed Price dominates the cost stack. A shorter economic life assumption — driven by degradation beyond contract expectations — would push the component higher and test the IRR cap.

Article 7 · Circular 62/2025/TT-BCT

Fixed O&M Price methodology

The Fixed O&M Price recovers major repair costs, minor repair and periodic maintenance costs, labour costs, and other annual operating costs. It is calculated as an annualised VND/kWh component.

In practice: BESS O&M in 2026 is materially lower than thermal-plant O&M — typically USD 3–7/kWh/year for containerised LFP systems with BMS monitoring — which works in Circular 62's favour versus legacy generation pricing frameworks.

Variable Price · Circular 62/2025/TT-BCT

Charging-cost recovery methodology

The Variable Price recovers the cost of charging electricity, computed from the BESS's self-consumption rate, the transmission-loss rate during charging, and the off-peak retail tariff for manufacturing industries. Under Decision 1279/QĐ-BCT currently in force, the off-peak manufacturing rates are VND 1,146/kWh at ≥110 kV, VND 1,190/kWh at 22 kV to <110 kV, VND 1,234/kWh at 6 kV to <22 kV, and VND 1,300/kWh at <6 kV.

In practice: the Variable Price calculation creates a direct linkage between retail tariff adjustments and BESS economics. A future uplift in off-peak manufacturing rates — for example from the pending Decree 72 amendment allowing EVN loss-recovery — raises the Variable Price proportionally, which widens the headroom under the pricing ceiling for project returns.

PPA provisions · Circular 62/2025/TT-BCT

Power Purchase Agreement mandatory contents

Circular 62 prescribes the minimum contents of BESS Power Purchase Agreements, including pricing and adjustment mechanisms, foreign exchange adjustment, settlement rules, and change-in-law provisions. This regulated-PPA approach — rather than a freely negotiable template — is consistent with Vietnam's treatment of solar, wind, and thermal PPAs.

In practice: the regulated PPA is bankability-positive for lenders (standardised risk allocation) but limits the scope for commercial creativity. Transactions that need non-standard terms will likely require side letters or amendments negotiated within the permitted discretion of the regulated text.

Commercial implications

Circular 62 is the regulation that makes Vietnam's 10,000–16,300 MW standalone BESS target commercially possible. Before it took effect there was no pricing mechanism, no standardised PPA, and no published investment envelope — and deployment was correspondingly zero. With Circular 62 in force, the unit economics of a utility-scale BESS project in Vietnam can be modelled, debt-financed, and contracted for the first time. The constraint is no longer regulatory clarity but implementation precedent: how the annual price bracket lands in its first approval cycle, how dispatch rules resolve, how FX adjustment plays through in practice.

  • For utility-scale BESS developers The regime is now workable. First-mover positioning matters because the 2026 annual approval cycle will set pricing precedent for subsequent years. Projects in preparation should prioritise feasibility-study completion to feed the 2026 pricing dossier deadlines, and should lock in FX-adjustment mechanisms against VND depreciation in PPA drafting. See the wholesale-market framework for data centres →
  • For lenders and project finance The dual-revenue structure transforms BESS from an unbankable merchant asset into something that can be debt-financed against a capacity-payment stream. The 12% IRR cap is tight but matches emerging-market norms for first-of-a-kind asset classes. Key underwriting questions: what capacity factor does the price bracket assume, how does the annual adjustment mechanism flow through to the PPA, how is lender step-in handled under the regulated PPA.
  • For C&I clients (factories, data centres) Circular 62 does not apply directly. Behind-the-meter BESS at a factory or data-centre site is governed by the retail tariff — Decision 1279 today, Decree 146 two-part tariff from 1 July 2026 for large manufacturers. The Pattern D spokes Circular 62 for factories → and Circular 62 for data centres → exist to explain the indirect effects — grid-stability improvements, renewable integration tailwinds, and the possibility of signing virtual PPAs with standalone BESS projects in future — rather than to suggest Circular 62 governs C&I BESS investment.

Vietnam becoming the first major ASEAN economy to adopt a formal two-part tariff for BESS is a structural regulatory advantage the wider region does not currently match. For investors weighing Southeast Asia BESS exposure, Vietnam 2026 is the jurisdiction where the pricing framework has moved from aspirational to operational. The question is no longer whether Vietnam will deploy meaningful utility-scale storage — the legal machinery is now in place — but how fast the first cohort of projects converts regulatory clarity into financial close.

Worked example

Indicative scenario · 50 MW / 200 MWh standalone BESS, Ninh Thuan

A utility-scale BESS at a 110 kV substation in Vietnam's highest-renewable province

Setup

  • Project typeStandalone grid-connected BESS, first-mover location
  • LocationNinh Thuan — highest renewable penetration and most acute curtailment in Vietnam
  • Rating50 MW / 200 MWh (4-hour LFP duration, within PDP8 revised allocations)
  • Grid connection110 kV substation, direct to regional transmission network
  • Capex (installed)USD 250/kWh all-in → USD 50 million total (April 2026 LFP utility-scale; briefing benchmark USD 250–350/kWh)
  • FX spotVND 25,500 / USD (April 2026)
  • Economic life15 years
  • Cycle count~350/year (daily dispatch less Sundays and maintenance)
  • Depth of discharge~85% nameplate (LFP convention, preserves warranty-compliant cycle life)
  • Round-trip efficiency~85% AC-AC (auxiliary loads, transformer losses included)
  • CounterpartyEVN via regulated PPA under Circular 62

Indicative annual revenue stack (USD millions)

Revenue / cost component Mechanism Indicative
Capacity paymentAvailability-based — paid regardless of dispatch4.5–6.5
Energy paymentPer-kWh delivered during dispatch cycles3.5–5.0
Gross annual revenue8.0–11.5
Charging cost (Variable Price basis)At ≥110 kV off-peak manufacturing rate × charging MWh(2.5–3.5)
O&M, insurance, adminRoutine operating costs(1.0–1.5)
Net operating revenue4.5–6.5

At USD 50 million of installed capex, a net operating revenue of USD 4.5–6.5 million per year implies a gross project yield in the 9–13% range before debt service, tax, and degradation reserves. This is consistent with the 12% IRR cap reported to apply under Circular 62. The project becomes bankable when debt-sized against the capacity payment alone — typically 50–60% gearing against a committed capacity revenue stream produces an equity IRR above 15% with the energy payment as upside. The critical modelling inputs are the annual price bracket level (not yet set for year one), the FX adjustment mechanism's responsiveness to VND depreciation, and the dispatch-rule implementation that determines actual energy-payment volume.

Source: Arcus Energy project analysis, indicative only — not a live project. Capex reference: April 2026 LFP BESS utility-scale market pricing (USD 250–350/kWh all-in installed). Regulatory references: Circular 62/2025/TT-BCT Articles 5, 7, and PPA provisions; Decision 1279/QĐ-BCT for the ≥110 kV manufacturing off-peak benchmark used in the Variable Price calculation.

Frequently asked questions

What is Circular 62/2025/TT-BCT?

Circular 62/2025/TT-BCT is Vietnam's first standardised pricing framework for standalone grid-connected battery energy storage systems. Issued by MOIT on 10 December 2025 and effective 26 January 2026, it applies to BESS projects of 10 MW or more connected at 110 kV or higher and developed under the revised Power Development Plan VIII. It establishes an annual price bracket, mandatory Power Purchase Agreement contents, and a dual-revenue capacity-plus-energy payment structure.

Which BESS projects does Circular 62 govern?

Only standalone grid-connected BESS meeting three cumulative conditions: capacity at or above 10 megawatts, grid connection at 110 kilovolts or higher voltage, and inclusion under PDP8 revised (Decision 768/QĐ-TTg, April 2025). BESS integrated with renewable power plants is governed by Circular 12/2025/TT-BCT instead; BESS owned by Power Corporations is governed by Circular 17/2025/TT-BCT; behind-the-meter C&I BESS at factory or data-centre sites is governed by retail tariff regulations, not Circular 62.

What are the three components of the BESS price ceiling?

The maximum generation price under Circular 62 is the sum of three components. The Average Fixed Price recovers the annualised cost of construction investment capital divided by the average electricity delivered and received over the BESS's economic life. The Fixed O&M Price recovers major and minor repair costs, labour, and other annual operating costs. The Variable Price recovers the cost of charging electricity, calculated against the self-consumption and transmission-loss rates and the off-peak retail tariff for manufacturing industries under Decision 1279/QĐ-BCT.

Does Circular 62 apply to behind-the-meter BESS at factories or data centres?

No. Circular 62 governs standalone grid-connected BESS that supply power to the national grid; it does not apply to behind-the-meter C&I storage at customer sites. A factory or data centre installing BESS for peak-shaving and energy arbitrage is operating under the retail-tariff regime set by Decision 1279/QĐ-BCT, and from 1 July 2026 for eligible large manufacturers, the two-part retail tariff set by Decree 146/2025/NĐ-CP.

What is the dual-revenue structure?

Circular 62 introduces a two-part tariff for BESS: a capacity payment for grid availability regardless of dispatch, plus an energy payment for electricity actually delivered during dispatch cycles. The capacity payment provides predictable cash flow that supports debt service and improves bankability, while the energy payment compensates operational delivery. This mirrors the structure used in mature storage markets such as PJM and the UK capacity market and is the first time a major ASEAN economy has adopted this structure for storage.

How is the annual price bracket approved?

The process runs annually. Within 15 days of a project feasibility study being approved, the investor submits a pricing dossier to EVN. Before 1 November each year, EVN aggregates submissions and proposes the following year's price bracket to the Electricity Department under MOIT. The Electricity Department appraises the submission and reports to the MOIT Minister for approval. The approved bracket sets the envelope within which individual project prices are bilaterally negotiated.

Is the 12% IRR cap hard?

The 12% internal-rate-of-return cap is set on a pre-tax nominal WACC basis under Circular 62's Average Fixed Price methodology (Article 5). The cap is structural to the pricing formula — it constrains how the Average Fixed Price component can be set — rather than a separately applied override. Whether it binds in practice depends on the approved annual price bracket, which has not yet been issued for any year. First-mover projects reaching financial close in 2026–2027 will establish the operating precedent.

How does Circular 62 relate to the two-part retail tariff under Decree 146?

The structural logic is identical — both split compensation into a capacity component and an energy component — but the regulations apply to different sides of the meter. Decree 146 governs what large retail customers pay to EVN under the two-part tariff pilot from 1 July 2026. Circular 62 governs what standalone BESS owners receive from EVN under wholesale-market contracts. A single project cannot be governed by both; whether Decree 146 or Circular 62 applies depends on whether the BESS is a retail consumer's asset (behind-the-meter) or a grid-connected generation-service asset (standalone utility-scale).

Last updated · 23 April 2026 Canonical URL · arcusenergyasia.com/resources/regulations/circular-62